Our Pool Design Services

RecTec Management Group Inc. has an extensive background and knowledge in the design, construction, management and operation of many different types of aquatic facilities. We have developed a Phase System that has led to the success of many different projects from a minor upgrade to a multi million dollar upgrade or construction. Using the Phase System as the starting point, each project is customized to meet the needs of all our customers. As the phases move from concept to operation we can provide everything from written/drawn specifications to commissioning. With this system we can provide our services to a wide variety of customers like municipalities, design firms, swim clubs and private owners. Let us work for you!


PHASES TO NEW CONSTRUCTION

    PHASE I – THE NEED/AMENITIES OF THE POOL

  • Through meetings, fact finding, investigation and questioning, generate a feasibility study on the need, type, programs of the aquatic facility. The study will include potential partnerships and sponsors on the construction and operation of the facility.
  • Based on the feasibility study, provide details to assist with the potential location of the facility.
  • Determine the amenities required within the aquatic portion of the facility, along with any other special requirements of the owner and key stakeholders.
  • Provide budgetary numbers of the cost of construction based on the amenities requested. Each amenity within the pool areas will have a line item in the budget for easy reference.
  • Provide a projected schedule to completion through the planning and construction.
  • Provide projected yearly operational costs of the facility.

     PHASE II – THE DESIGN TEAM

  • Prepare project specifications and drawings for the tendering of pre-qualified design teams concepts.
  • Design Team could include Project Coordinator, Architect, Structural, Mechanical, Electrical Engineers, Building Science Engineers, Consultants, etc.
  • Confirm design and construction schedule for the project.
  • Assist in the evaluation of the Design Team proposals against the written specs, drawings and feasibility study.
  • Through the Design Team, prepare project specifications and drawings for building permit.
  • Through Design Team, prepare project specifications and drawings for the construction process.

     PHASE III – OVERSEE POOL/GENERAL CONTRACTOR

  • Review project specifications and drawings for construction tender process.
  • Evaluate bids from pre-qualified General or Pool Contractors.
  • Evaluate the pre construction drawing submittals from successful General Contractors.
  • Review and inspect critical points during construction against the specifications and drawings.
  • Final evaluations and commissioning of the facility over to the Owner.
  • Review As-Constructed Drawings and submittals from the General Contractor.

                         




PHASES TO EXISTING FACILITY UPGRADES

      

     PHASE I – THE NEED/AREAS OF UPGRADE

  • Through meetings, fact finding, investigation, inspect and questioning generate a report on the areas of the aquatic facilities that require expansion or upgrades.
  • If the project requires expansion, follow the same system as listed above under new construction.
  • If the project requires renovations or upgrades, based on the information collected above determine the upgrade areas required, along with any other special requirements from the owner and key stakeholders.
  • Provide budgetary numbers of the cost of the project based on the upgrades requested. Each upgrade will have a line item in the budget for easy reference.
  • Provide a projected schedule to completion for the project.
  • Provide projected yearly operational costs of the upgrades.

     PHASE II – THE DESIGN TEAM

  • Prepare project specifications and drawings for the tendering of pre-qualified design teams. 
  • Design Team could include Project Coordinator, Architect, Structural, Mechanical, Electrical Engineers, Building Science Engineers, Consultants, etc.
  • Confirm design and construction schedule for the project
  • Assist in the evaluation of the Design Team proposals against the written specs, drawings and feasibility
  • study.
  • Through Design Team, prepare project specifications and drawings for building permit
  • Through Design Team, prepare project specifications and drawings for the work to be completed.

     PHASE III – OVERSEE POOL/GENERAL CONTRACTOR

  • Prepare project specifications and drawings for work tender process
  • Evaluation of bids from pre-qualified General Contractors
  • Evaluation of the pre-work drawing submittals from successful General Contractor.
  • Review and inspection at critical points during the project against the specifications/drawings and generate findings.
  • Final evaluations and commissioning of the facility over to the Owner.
  • Review of As Constructed Drawings and submittals from the General Contractor.

                   